Lyon-Turin #singleconstructionsite: progress November 2026
Update on the work on the Mont Cenis base tunnel between Italy and France and on above-ground works.
Works on the Mont-Cenis base tunnel are progressing, with 14 excavation faces currently active. As of mid-October 2026, more than 50 km of tunnels had been excavated out of the 164 km planned.
In October, the Viviana tunnel boring machine (TBM) at Saint-Martin-la-Porte (CO7) passed through the fault zone and resumed excavation at its regular pace. On 7 November, it reached the bypass, where it stopped to allow the teams to carry out scheduled maintenance operations, which will continue until the end of the year.
Meanwhile, conventional excavation works are continuing in both directions, towards Turin and Lyon. Activities are also progressing in the La Praz (CO6) section, where components for the first of the two TBMs intended to excavate the section towards Modane are arriving. At the CO5 site, assembly of the first of the two Gripper-type TBMs, which will cross the French-Italian border, is well underway. Excavation is scheduled to begin next spring. At the same time, reinforcement works and construction of the permanent lining of the penultimate ventilation shaft of the tunnel (CO5a) are continuing.
At the French entrance to the base tunnel, in Saint-Julien-Montdenis (CO8), conventional excavation is nearing completion, while work on the permanent lining is progressing. In October, concreting of the vault in the south tube reached 1,556 metres. Installation of the waterproofing system and construction of the permanent lining have also begun in the north tube.
In the Saint-Jean-de-Maurienne (CO9) plain, the second phase of the railway connection works to the existing line, carried out by SNCF Réseau, has been completed. The line has been reopened to traffic with the new track layout towards the base tunnel, allowing the third phase of works to begin. Since the summer, construction of the bridge over the Arc river has also been underway.
On the Italian side, at Chiomonte (CO3/4), restoration works at the construction site, following the damage caused during the violent demonstration on 25 July, are almost complete. Preparatory works to develop the area ahead of the start of excavation of the Maddalena 2 access tunnel, through which the TBM will reach the underground construction site, will be carried out when work resumes. These activities remain within the overall project implementation schedule.
Finally, at the sites dedicated to the recovery and reuse of excavated materials in Salbertrand, Susa and Torrazza Piemonte (CO10), site preparation works are continuing. In Salbertrand, assembly of the structures for the new facility is underway. In Torrazza, construction of the structures for the conveyor belts is progressing, while at Susa, work on the installation of utility networks is continuing across the site.