Rail connections to the existing line and construction of the new international station.
Inaugurated in June 2022 as part of Phase 1, the Saint-Jean-de-Maurienne multimodal interchange hub (PEM) ensures continuity of connections and access to the station during the rail interconnection works. It also prepares for the arrival of the Mont Cenis base tunnel and the creation of a future international station, facilitating connections between different modes of transport: trains, buses, cars and bicycles.
Completed in October 2026, Phase 2 included, among other works, the installation of 11 km of new railway tracks and 16 km of overhead contact lines.
Works are continuing with Phase 3, scheduled to run until 2028. These include the construction of the second deck of the Arvan viaduct, the permanent reinstatement of the railway track serving the TRIMET plant, the construction of the new railway platform for the existing line, the construction of a second bridge allowing the RD 906 road to pass beneath the railway tracks, and the relocation of the RD 1006 road.
Construction site photos
Key data
0
-2030: temporary configuration of the multimodal hub
0
Opening of the international station
0 m³
of railway embankment material
0
people on the construction site
Companies involved in the works
Rail interconnections are being delivered by SNCF Réseau on behalf of TELT, for a total value of approximately €800 million. Two civil engineering contracts have been awarded by SNCF Réseau: the first, worth €189.5 million over nine years, to Eiffage Génie Civil, and the second, worth €24 million over three years, to TSO SAS (starting in May 2025).
Temporary multimodal interchange hub
In July 2022, the new temporary hub replacing the former station was inaugurated to prepare the connection of the existing railway lines to the new base tunnel. To support passengers and keep stations operational during the works, TELT and SNCF Réseau built a temporary multimodal interchange hub, facilitating connections with other transport systems.
At the same time, a new road network was created to integrate the new station into its surroundings and improve links with neighbouring districts. Preparatory works were also carried out in the southern area of the Saint-Jean-de-Maurienne basin, in order to free up the space that will accommodate the new tracks near the base tunnel entrance.