Eight excavation fronts for the base tunnel
With the completion of the third pilot hole and the boring of the first shaft, excavation work on the four ventilation shafts of the Mont-Cenis base tunnel in the Avrieux area is continuing. On 13 February, the second reamer completed the pilot hole for shaft 3 and was then moved to drill the fourth and final hole, while by the end of the month the Raise Boring Machine had reached a depth of 373 metres out of the 500 metres planned for the first shaft.
At the foot of the Villarodin-Bourget/Modane access adit, work is continuing on the two excavation fronts of the network of galleries forming the safety site. The deepening of the 77-metre-long intersection cavern is progressing and will provide the required cross-section to continue excavation of the base tunnel tube towards Italy. Meanwhile, excavation of the connecting gallery between the two base tunnel tubes, which will house the Modane underground safety site, has reached 228 metres out of a total of 575 metres.
The Eiffage-Spie Batignolles-Ghella-Cogeis consortium, awarded the contract for excavation of the base tunnel from the Modane worksite, has ordered the two tunnel boring machines, each 10.43 metres in diameter, that will excavate the railway tunnel section between the Modane and Clarea safety sites.
At Saint-Julien-Montdenis, excavation of the two base tunnel tubes is continuing under the protection of pipe umbrellas, from the western portal towards Saint-Martin-la-Porte. More than 150 metres have been excavated to date.
In Italy, excavation of the vehicle turning bays inside the Maddalena tunnel at Chiomonte is more than 60% complete. Outside the tunnel, replacement of the rockfall protection net protecting the construction site is nearing completion, while the company responsible for building the new motorway interchange on behalf of Sitaf has installed the site offices and is carrying out preliminary works.
At the same time, the electrical and heating distribution systems for the new visitor centre have been completed, and the geothermal heat pump and storage tanks have been installed. This will make it possible to use the hot water intercepted during excavation of the geognostic tunnel to heat or cool the visitor area. The related connections are currently being installed.
Finally, at San Didero, where motorway concessionaire Sitaf, operating under an agreement with TELT, has awarded the works for the new autoport, demolition of the existing buildings in the area has been completed and preparatory activities for the construction of the motorway access ramps have begun.