Chiomonte site

The construction site of the Turin-Lyon high speed rail line (Tav), Val di Susa Torino 09 agosto 2019 ANSA/TINO ROMANO
The construction site of the Turin-Lyon high speed rail line (Tav), Val di Susa Torino 09 agosto 2019 ANSA/TINO ROMANO

DECLINE AND BASE TUNNEL | 7 KM | WORK COMPLETED

This is the largest Italian construction site for the Lyon-Turin line. The Chiomonte geological survey tunnel, completed in February 2017, was excavated to learn more of the structure of the mountain where the new Lyon–Turin line will run through. It is the Italian access route to the base tunnel construction site.

Progress

15.02.2017
100%

The excavation was conducted mainly with mechanical means, using the “Gea” TBM, under an overburden of about 2,000 m of mountain. Since 2012 it has been a site of national strategic interest and today the site maintenance activities are underway in view of the start of the final works.

Niches et retournement

The Maddalena tunnel started as an exploration tunnel. Today, the construction site variant foresees that the excavation of the base tunnel will start from Chiomonte instead of Susa and therefore it is necessary to adapt the tunnel in order to allow construction vehicles to pass through. 23 interchange niches will be built and inserted as recesses along the exploratory tunnel.

During the excavation of the base tunnel, this exploratory tunnel will be used as service access for the circulation of vehicles and equipment on the construction site and as ventilation system. These niches will be 30 to 40-m-long, 3-metres-deep areas that will allow vehicles to cross over safely. They will be excavated using the traditional method over a period of 19 months. This will start the transition of the construction site to the construction phase of the base tunnel.

Variant project

A variation of the final project was approved by the CIPE (Interministerial Committee for Economic Planning) in March 2018, following the Security Study conducted by the National Interuniversity Consortium for Transport and Logistics (NITEL), consisting of 20 Italian universities with over 500 researchers. According to this variation, and in order to ensure the safety of workers and citizens, the main activities for the construction of the base tunnel in Italy will start from the Chiomonte construction site (instead of from Susa as originally intended).

The site will expand by 4 hectares to a total of 12, extending under the viaduct of the A32 motorway to the municipalities of Chiomonte and Giaglione, in an area already used by SITAF during the construction of the motorway. At approximately 40 m from the first tunnel, a second one will be built parallel to the survey tunnel, having the same diameter as the base tunnel. During work, this will be the access point for the TBM which will begin boring towards Susa, while, once operational, the first section of the tunnel will be used for ventilation and smoke extraction for the base tunnel and as the Clarea safety site, and, in the second section, for the possible definitive storage of green rocks.

The construction of a safety site and of a ventilation centre for both the tunnel and this site is also planned. The centre is designed with a semi-underground solution, with terraces planted with greenery, and rows of vines and apple trees so as to integrate it seamlessly in the territory. It is foreseen to use materials such as weathering steel, wooden slats and local stone. The new configuration was deemed by the competent authorities to be the most suitable for ensuring safety while maintaining soil consumption to a minimum and limiting environmental impacts.

VIS

The rigorous environmental controls carried out on the site led to the implementation of the Health Impact Assessment, in collaboration with the University of Turin. 

Since 2012, in fact, the main environmental pressure factors in the work area have been monitored: over 62,000 measurements have indicated a situation of compliance with the values.